Agenda

Section Number Topic Number Details
I. Opening Items
  A. Record Attendance
  B. Call the Meeting to Order
II. Expansion Focus Group
  A. Funding Update
  B. Budget Items
   

Short - Term: Staff, Furniture, Curriculum

 

Long - Term: Staff, Furniture, Curriculum, Building

  C. Master Plan
   

What is needed?

What decisions are needed?

What timeline can we work within?

 

Timeline to talk with Anser Advisory & DCS

  D. Additional Site & Building work
   

1. Plumbing connections 

2. Electrical connections 

3. Foundation preparation 

4. Fence removal and storage with construction fencing to separate playground from adjacent construction site followed by re-installation of fencing with needed modifications to adapt to new building after modular is delivered and set-up.

5. Excavation needed to allow traffic flow and additional parking spaces to be installed to accommodate additional students,  teachers,  parents and service providers for a larger operation.

6. Fire alarm system installation and connection to our Simplex fire panel.

7. Locksmith services to maintain common keying. 

8. Concrete walkways installations around new building. 

9. Landscaping installation and general grounds repairs to correct the damages associated with the many steps of the construction process.

  E. Tasks for follow up
   

Next meeting

III. Other Business
IV. Closing Items