Alma del Mar

Finance Committee Meeting

Published on June 19, 2020 at 12:53 PM EDT

Date and Time

Friday June 19, 2020 at 11:00 AM EDT

Location

Remote
Join Zoom Meeting
https://us02web.zoom.us/j/83724328337?pwd=cE5WNUhwdmczQmxGQlpNdnpsMEl2QT09

Meeting ID: 837 2432 8337
Password: 550121
One tap mobile
+13126266799,,83724328337#,,,,0#,,550121# US (Chicago)
+16468769923,,83724328337#,,,,0#,,550121# US (New York)

Dial by your location
        +1 312 626 6799 US (Chicago)
        +1 646 876 9923 US (New York)
        +1 301 715 8592 US (Germantown)
        +1 669 900 6833 US (San Jose)
        +1 253 215 8782 US (Tacoma)
        +1 346 248 7799 US (Houston)
        +1 408 638 0968 US (San Jose)
Meeting ID: 837 2432 8337
Password: 550121
Find your local number: https://us02web.zoom.us/u/k54NEhTgn

Agenda

     
I. Opening Items
  A. Record Attendance
  B. Call the Meeting to Order
  C. Approve Minutes
    Approve minutes for Finance Committee Meeting on May 22, 2020
  D. Approve Minutes 8/16/2019
   
II. Finance
  A. FY20 May Financials
  B. Construction Project Update
   
Overview of updated timeline for the construction of the Frederick Douglass Campus
Architects slated to complete design in July and groundbreaking is planned for August/September.  Financing with EFF planned for late September.  Anticipated building completion is December 2021.

 

Overview of the funding needs for pre-construction, groundbreaking and early phase construction
There is currently enough cash on hand and incoming pledge payments to pay for pre-construction and site work through September.  If the financing closing is pushed into October and the project stays on track, there will be a cash outlay need of $1.7 million for the steel delivery.

 

Overview of Project Budget and fundraising needs to complete the project
Project Budget:           $24,867,845
Paid to Date:                 (1,581,565)   (Land, Design Phase, Other PreDevelopment)
Cash on Hand:               (553,991)
Outstanding Pledges:    (1,115,000)   (Commitment dates of 12/31/2020)
EFF Loan:                     (20,000,000)  (Expected to close late September)

 

Amount to Raise           $1,617,289
  C. 5 Year Capital Plan
III. Other Business
  A. Schedule Special Meeting in July
IV. Closing Items
  A. Adjourn Meeting