Elgin Math & Science Academy

April Master Planning Meeting

Date and Time

Wednesday April 14, 2021 at 11:00 AM CDT

Location

Elgin Math and Science Academy is inviting you to a scheduled Zoom meeting.
Topic: EMSA Master Planning
Time: Apr 14, 2021 11:00 AM Central Time (US and Canada)

Please download and import the following iCalendar (.ics) files to your calendar system.
Daily: https://zoom.us/meeting/tJwsdu2uqDwjHNeZAy64V-dwbPpKcN42WL0O/ics?icsToken=98tyKuCgrzouHNKSuR-ERow-BYj4LO7wpmZEgo1Ypj78VXRlLwfhNNJSGbFRRIrn
Join Zoom Meeting
https://zoom.us/j/98114667963?pwd=d0l3YzdnY01udnNpSy84aHlzSFpiQT09
Meeting ID: 981 1466 7963
Passcode: EMSA
One tap mobile
+13126266799,,98114667963#,,,,*578054# US (Chicago)
+19292056099,,98114667963#,,,,*578054# US (New York)
Dial by your location
        +1 312 626 6799 US (Chicago)
        +1 929 205 6099 US (New York)
        +1 301 715 8592 US (Washington DC)
        +1 253 215 8782 US (Tacoma)
        +1 346 248 7799 US (Houston)
        +1 669 900 6833 US (San Jose)
Meeting ID: 981 1466 7963
Passcode: 578054

Agenda

     
I. Opening Items
 
Opening Items
  A. Record Attendance and Guests
  B. Call the Meeting to Order
  C. Approve Minutes
    Approve minutes for March Master Planning Committee Meeting on March 17, 2021
II. Master Plan Business
 
Master Plan Committee
  A. COO report
   
Buildings Report:

 

1.  Change in Cleaning Vendor

 

 

 

 

 

 

 

 

 

 

III. Construction--Specific Items
  A. Construction Report: Schedule, Budget, and Decisions
   
The project continues to track to be on-schedule, and under budget for the defined scope of the Gym Project plus Warm Safe and Dry.

 

COO Report on Gym/Middle School Project
Master Project Budget Tracking Document

 

Decisions: 
  B. Kitchen Equipment
   
Grant availability
Re-use capabilities
  C. Contingency Allocated Spending
   
The Master Planning Committee with vote on utilizing owner contingency for change orders, scope additions, equipment or other needed improvements.  See blue tracking document items: 22-24 for consideration. 
IV. Campus Strategic Planning
  A. “Warm Safe and Dry” Update
  B. Facility Use Planning
V. Residential Building
  A. Maintenance and Repairs
   
The master planning committee will discuss and vote on the approval of a budget and repairs necessary for the residential building on EMSA's campus.
VI. Environmental Subcommittee and Grounds Issues
  A. Subcommittee update
   
  • Update on Oaks & plantings
  • Visit by Davey Tree
  • Update on Swing set location
  • Visit by Conservation Foundation 3/26
  • Hiking/running trail--next steps
  • Family hikes
VII. Closing Items