Lake George Charter School

Expansion Mar Update

Published on March 15, 2023 at 9:16 PM MDT

Date and Time

Thursday March 16, 2023 at 4:30 PM MDT

Agenda

      Purpose Presenter Time
I. Opening Items 4:30 PM
  A. Record Attendance   1 m
  B. Call the Meeting to Order  
II. Expansion Focus Group 4:31 PM
  A. League of Charter Schools Conference recap Discuss Brian & Dr Wade 10 m
   

Important contacts

Individuals/Organizations we need to follow-up with

 
  B. Master Plan Discuss 25 m
   

What is needed?

What decisions are needed?

What timeline can we work within?

 

 
  C. Additional Site & Building work Discuss 15 m
   

1. Plumbing connections 

2. Electrical connections 

3. Foundation preparation 

4. Fence removal and storage with construction fencing to separate playground from adjacent construction site followed by re-installation of fencing with needed modifications to adapt to new building after modular is delivered and set-up.

5. Excavation needed to allow traffic flow and additional parking spaces to be installed to accommodate additional students,  teachers,  parents and service providers for a larger operation.

6. Fire alarm system installation and connection to our Simplex fire panel.

7. Locksmith services to maintain common keying. 

8. Concrete walkways installations around new building. 

9. Landscaping installation and general grounds repairs to correct the damages associated with the many steps of the construction process.

 
  D. Tasks for follow up Discuss 10 m
   

Next meeting

 
III. Other Business
IV. Closing Items
  A. Adjourn Meeting Vote